Yaita
Yaita, JapanPhotovoltaic solar
The Yaita solar farm with 41 MWp of capacity has been build on a former gulf course. the duration of the project was 11 months and mobilized up to 100 people at peak.
Project activities
Main company
BOUYGUES Energies & Services
Activities
Construction, Developer of energy production plants, Operation and maintenance
Type of implantation in the country
Subsidary
Project Information
Detail of the equipment used
122000 PV modules Schneider's inverters
Installed power (specify unit KW, MW or other)
41 MWp
Annual produced energy (specify unit MWh or other)
60 GWh
Grid connection
On grid
Main fundings
Equity, debt
Project cost (in euros)
45 000 000 €
Year of entry into service
2018
Project progress
Employees mobilized
-
100
Locals employees
-
10
Employees for the development phase
-
100
Employees for the construction phase
-
5
Employees for maintenance
Main company
BOUYGUES Energies & Services
- Biogas , Onshore , Photovoltaic solar , Hydropower , Energy efficiency
- Construction , Developer of energy production plants , Operation and maintenance , Storage
Main french partners
Lead company in charge of the project : EQUIS / NRE
Main partners : Schneider
Main non-french partners
Toho group (JPN)