Project

Arkona

Germany

Offshore

Arkona (Allemagne)

STX France is in charge of the EPCIM contract of the offshore electrical substation of Arkona, one of the largest HVAC offshore substation (385 MW) ever built due for delivery in 2018. The substation will be installed in the Baltic sea in Germany, where is located the offshore wind farm of Arkona. The owner of the farm are E.ON, Statoil and 50hertz.

This giant 385 MW station, which will be one of the largest in the world, will have a topside of more than 4,000 t.

Project activities

Main company

STX France

Activities

Construction

Type of implantation in the country
Joint-venture
Project Information
Installed power (specify unit KW, MW or other)

385 MW

Annual produced energy (specify unit MWh or other)

-

Grid connection

On grid

Main fundings

Equity

Project cost (in euros)

1 200 Millions €

Year of entry into service

2018

Project progress

Contract signed
Work in progress
In operation
Employees mobilized
  • 200

    Locals employees

  • 50

    Employees for the development phase

  • 150

    Employees for the construction phase

  • 15

    Employees for maintenance

Main company

STX France

  • Offshore
  • Construction
  • SER Member
Main non-french partners
  • Schneider
  • ABB
  • SHL
The project photo gallery