This 120 MW wind park is localized in Porteiras, Ceará state, Brazil. The commissioning is planned at the beginning of 2021.
Project activities
Main company
Qair
Activities
Development, Construction, Developer of energy production plants, Operation and maintenance, Power generator, Support profession
Type of implantation in the country
Subsidary
Project Information
Detail of the equipment used
4 MW windturbines - Grid connection 132 kV
Installed power (specify unit KW, MW or other)
120 MW
Annual produced energy (specify unit MWh or other)
420 GWh
Grid connection
On grid
Main fundings
Equity, debt
Project cost (in euros)
120 000 000 €
Year of entry into service
2021
Project progress
Employees mobilized
-
500
Locals employees
-
8
Employees for the development phase
-
500
Employees for the construction phase
-
20
Employees for maintenance