Project 889 - Bumva
Bumva, RDC (Congo)Hydropower
Design, manufacturing, installation and commissioning of 4 Double Francis turbines of 5.4 MW each.
Project activities
Main company
HPP
Activities
Equipment manufacturer
Project Information
Detail of the equipment used
Turbines, alternators, control panels, SCADA, communication system, 11kV switchgear, auxiliary transformers and diesel back-up engines
Installed power (specify unit KW, MW or other)
21 600
Annual produced energy (specify unit MWh or other)
Nc
Grid connection
On grid
Project cost (in euros)
Nc
Project progress
Employees mobilized
-
-
Locals employees
-
-
Employees for the development phase
-
-
Employees for the construction phase
-
-
Employees for maintenance