Hydropower

Design, manufacturing, installation and commissioning of 2 Pelton turbines of 2.75 MW each.

Project activities

Main company

HPP

Activities

Equipment manufacturer

Type of implantation in the country
Subsidary
Project Information
Detail of the equipment used

Inlet Valve, Turbine, Generator, HPU

Installed power (specify unit KW, MW or other)

2,75 MW

Annual produced energy (specify unit MWh or other)

5 500

Grid connection

On grid

Project cost (in euros)

Nc

Project progress

Contract signed
Work in progress
In operation
Employees mobilized
  • -

    Locals employees

  • -

    Employees for the development phase

  • -

    Employees for the construction phase

  • -

    Employees for maintenance