Project

Project 1354 - Jharipani

Jharipani, India

Hydropower | Access to energy

r628_9_1354_hpp_jharipani-2.jpg

Design of an horizontal Pelton turbine 2 jets of 685 kW. Manufacturing of the Pelton runner  in the context of a refurbishment of an hydro power plant.

Project activities

Main company

HPP

Activities

Equipment manufacturer

Project Information
Detail of the equipment used

Turbine Design, runner

Installed power (specify unit KW, MW or other)

685 kW

Annual produced energy (specify unit MWh or other)

Nc

Grid connection

Off grid

Project cost (in euros)

Nc

Project progress

Contract signed
Work in progress
In operation
Employees mobilized
  • -

    Locals employees

  • -

    Employees for the development phase

  • -

    Employees for the construction phase

  • -

    Employees for maintenance

Main company

HPP

  • Hydropower , Access to energy
  • Equipment manufacturer
Share
EN FR